November 20, 2003 Year end progress report
|
|||||||||||
|
Rivers Edge Trail - 2003 Progress
Completed construction of the Giant Springs Road Trail Tunnel Completed final design, contract documents for Phase 1, Bay Drive Trail Completed Phase 2 of the Ryan Trailhead on the North Shore Trail Completed fencing, turnstile and temporary Morony Trailhead Designed and completed the Rainbow Trailhead on the North Shore Trail Completed Phase 1 stabilization and repairs to the Ryan Stone Building Wrote successful CTEP grant to fund design of Phase 2, Bay Drive Trail Organized and staffed a successful 2003 Blues & Brews fundraiser Worked with Great Falls Tribune to produce River's Edge Trail Map and Guide With MCC, built and installed 3 new trailhead information kiosks With MCC, continued extensive cleanup along North Shore conservation easement Mulched and watered young trailside trees throughout the dry year Assisted with River Corridor, Bike/ped Facilities and West Bank Park planning Worked with PPL MT to open the Cochrane Dam Trail Crossings for 16 days Completed final re-design of West Bank and Black Eagle Trail projects Completed geotech work and initiated design for B. E. Island access road repairs Organized 100s of hours of trail cleanup, weed control, maintenance projects Assisted with Whitmore Ravine inventory, mapping and assessment Seal coated 3 miles of trail, trail edge weed control on 7 miles of trail Raised and matched donations with federal grants and special projects Added first trailside sculpture, a wind-driven trout, near the Weissman Bridge Rivers Edge Trail - 2004 Goals Complete construction of Phase 1 of the Bay Drive Trail Complete construction of trail segments between the Refinery and B. E. Island Add memorial shelters, benches, tables and trees to these new trail segments Complete construction of upper and lower road access, parking at B. E. Island Complete Morony Trailhead, linkages to North Shore and Sulphur Springs Trails Complete design and secure construction funding for Phase 2, Bay Drive Trail Complete entry towers, donor/interpretive panels, dedicate Weissman Bridge Complete exterior painting of boxcar and caboose, add trees and landscaping Work with PPL MT to continue public use of Cochrane Dam Trail Crossing Complete trail realignment and cleanup on the south end of Cochrane Dam Complete roadway signage to direct visitors to the 3 North Shore Trailheads Work with Great Falls Tribune to produce 2004 edition of Trail Map and Guide Plant new trees and vines for fences near WWTP on the West Bank Trail Organize and staff a successful 2004 Blues & Brews trail fundraiser Work with many partners to begin implementing Trail Interpretive Program Plan Seal coat 3 more miles of trail, repaint center-line and cross-walk striping Develop, print and distribute a pocket size fold-up Rivers Edge Trail Map Develop and install more permanent trail maps and information at kiosks Select and install a second trailside sculpture or art work Be sure and check out the 14 years and counting... |
|||||||||||